OneGov
App. Status: ApprovedAitkin County Planning & Zoning / Environmental Services
307 Second St. NW Room 219
Aitkin, MN 56431
Phone: 218-927-7342
Fax: 218-927-4372
Email: aitkinpz@aitkincountymn.gov
Contact Information
Enter Applicant Contact Information: |
|
||||||||||||||||||||||||||||||||
Are you the Property Owner? | Yes |
Property Location
Property Location: |
|
Project Checklist
1.) Is the property zoned Shoreland? | Yes |
2.) Is the property located in a flood zone? | No |
3.) Are there any wetlands or lowlands on/near the project site? | No |
4.) Will the structure(s) be used for commercial purposes? | No |
5.) Is there an existing septic system on the property? (Outhouse/Privies are also considered septic systems) |
Yes |
6.) Are you applying to install a new septic system? | No |
Existing Septic Status
Do you have a Certificate of Compliance, Certificate of Installation, Design for a new system, or does your project fall under Exemption A or B above? | Yes |
Project Description
Please describe your proposed project: | construct a 2 level 25 by 30 recreation structure. A 20 by 25 foot garage was removed and this new structure will be built on the same spot. Jody and associate (Brock I believe) came out in May and put flags identifying where I can put the structure. |
Project Type
Item 1 - Structure Type: | Accessory Building |
Item 1 - Type of Construction: | Wood/Frame |
Item 1 - Size: | 750 ft2 |
Shoreland Data
Setback distance from Ordinary High Water Level to the proposed construction? (closest point) | 150 Feet |
Will the proposed structure(s) be less than 35 foot maximum height? | Yes |
Are you constructing a walkout basement? | No |
Natural Landscape Protection Plan
Will there be any vegetation removal, earth moving, or fill placed in the Shore Impact Zone, Bluff Impact Zone or on a Steep Slope? | No |
How many cubic yards of fill or excavation will be done on the property? | 100 CuYd |
How close to the property line will any fill be placed or any excavation be done? | 20 Feet |
What percent slope of the land currently exists on the project site? | 20 % slope |
Select the erosion control methods that will be used throughout and after your project: (Check all that apply) |
Straw Bales Seeding and/or Mulching Rain Garden |
Other: | Since this structure will be placed on spot where garage was little excavation is necessary. I don't know the answer to #4 |
Site Plan
Please include all applicable items from the checklist on your site plan. See example site plan below: | All Existing Structures & Dimensions All Proposed Structures & Dimensions Location of Driveways & Access Roads Location of Well(s) Location of Septic System(s) Distance of Proposed Structures to OHWL (closest point) Distance of Proposed Structures to Septic System(s) Distance of Proposed Structures to Property Lines Distance of Proposed Structures to Road Right-of-Way Distance of Proposed Structures to Alley or Boulevard Distance of Proposed Structure to Top of Bluff |
Attach Site Plan: |
|
Is the site staked and ready for inspection? | Yes |
Additional Info
Additional info: (optional) |
attached septic inspection here. |
Attachments: (e.g. blueprints, floor plan, compliance inspection, or other information) |
Terms
All appropriate permit fees must be paid in full prior to review of the application.
Permit fees are non-refundable after a permit is approved.It shall be a violation of the Aitkin County Zoning Ordinance to commence construction before the permit application is approved by Aitkin County.
Zoning permits and Subsurface Sewage Treatment System permits are valid for one (1) year (unless the sewage permit is to upgrade an Imminent Threat to Public Health or Safety system, which is then valid for ten (10) months).
All corners of the proposed structure(s) need to be staked with visible flags, ribbon, or lathes prior to onsite inspection by Aitkin County.
Property lines need to be clearly marked or staked with visible flags, ribbon, or lathes prior to onsite inspection by Aitkin County.
Defining and staking the property lines, road right-of-ways, septic sites, and wells are the responsibility of the property owner. In some cases, a registered survey may be required to verify setbacks before granting a permit.After a complete application is submitted and reviewed, an on-site inspection may be conducted; a permit may be issued describing the proposed construction that may take place on the property. Changes to a project may require a permit application to be resubmitted.
The landowner or authorized agent may make application for a zoning permit agreeing to do such work in accordance with all Aitkin County Ordinances. The landowner or authorized agent agrees that the application, site plan, and all other attachments submitted herewith are true and accurate and shall become a part of the permit. The landowner or authorized agent agrees that, in making application for a zoning permit, the landowner grants permission to Aitkin County, at reasonable times, to enter the property to determine compliance of the application with applicable Local, County or State Ordinances or Statutes. It is the applicants sole responsibility to contact other Local, County or State agencies to ensure the applicant has complied with all relevant Local, County or State Ordinances or Statutes.
Applicants acknowledge that they are in compliance with MN Statute 326.121 subd 1 which states "The State Building Code is the standard that applies statewide for the construction, reconstruction, alteration, repair, use of buildings and other structures of the type governed by the code."
Applicants acknowledge that they are in compliance with MN Contractor Licensing laws per MN Statute 326B.85.
Applicants are responsible for getting all applicable entrance permits from the appropriate road authority.
I acknowledge that by submitting this application, the application and its attachments are public information.
Invoice #61268 (08/27/2024)
Charge | Cost | Quantity | Total |
---|---|---|---|
added 08/13/2024 10:10 AM $200 Flat Fee |
$200.00 | x 1 | $200.00 |
Grand Total | |||
Total | $200.00 | ||
Payment 08/27/2024 | $200.00 | ||
Due | $0.00 |
Approvals
Approval | Signature |
---|---|
Applicant | Darian K. Brend - 08/27/2024 3:12 PM bd721532af4b70ce7f58bec0c1df5251 6482f611665f979f8dcc76932f7668bf |
#1 Administrative Review | Jody Grund - 09/03/2024 9:54 AM 8c3c7ce318cf67b6db75fb485130d8f3 a69cc869b82896dcd06e230a3e6bb190 |
#2 Inspector Review | Jody Grund - 09/04/2024 3:35 PM 9e6643d32a38f60a46ccd30a3b7d99f9 6a036325931f21f850e4945d9c3aa701 |
#3 Final Approval | Connor Plagge - 09/05/2024 8:27 AM 2b9ad1ac7cdeaa4f189bc289b9511d5d e8564907fdb99aba5ae1c3a5ffe952a3 |
Public Notes
Text: | Permit #49001 Approved for a 750 sq ft Accessory Building |
File(s): |
|
Admin Checklist
Date application was complete: | 09/27/2024 |
Review started by: | Jody Grund |
Zoning District of project location: | Shoreland |
Required OWHL setback distance: | 100 ft. |
"Other" OHWL setback distance is: | |
Project located in the floodplain? | No |
Base Flood Elevation: | |
Lowest Floor Elevation: | |
Is an after construction elevation certificate required? | No |
Property line setbacks appear to be met? | Yes |
Road R-O-W setbacks appear to be met? | Yes |
Bluff setbacks appear to be met? | Yes |
Septic Tank setback appears to be met with/without an engineer's report? | Yes |
Septic Drainfield setback appears to be met with/without an engineer's report? | Yes |
Is the parcel a Lot of Record before 1-21-92 or have alternate sites been identified? | Yes |
Is this New Construction on a previously undeveloped lot or Redevelopment added to a developed lot? | Redevelopment |
Is this After-The-Fact? | No |
Inspector Checklist
Zoning Inspector: | Jody Grund |
Attach necessary inspection forms/photos: |
|
Notes: | approved for a 25 by 30 accessory structure. Setbacks appear to be met. |
Was an onsite conducted for this application? | Yes |