Land Alteration Permit # 47210, App. # App-2022-009259, UID # 205953
App. Status: Approved
Aitkin County Planning & Zoning / Environmental Services
307 Second St. NW Room 219
Aitkin, MN 56431
Phone: 218-927-7342
Fax: 218-927-4372
Email: aitkinpz@aitkincountymn.gov
 

Contact Information

If we have questions on the application who should we contact?
Name:
Charlene Hickerson
Phone:
(612237 - 9712
Email Address:
char47bh@aol.com
Mailing Address:
11701-95th ST NE
elk river MN 55330
Are you the Property Owner? Yes

Project Location Search

Property:
Property LocationLegal DescriptionProperty AttributesOwner InformationTax Payer Information
Parcel NumberProperty AddressTownship or City NameLegal DescriptionPlat NameSection-Township-RangeLake ClassLake NameOwner Name(s)Taxpayer Name(s)
07-0-02610640924 320th Ln
AITKIN, MN 56431
FARM ISLAND TWPS:12 T:46 R:27RDHANGING KETTLE LAKEHICKERSON, PAUL & KAYLAHICKERSON, PAUL & KAYLA
Driving directions to the property from Aitkin.:
4 miles south of Aitkin, MN. Turn onto 320th Lane. Go about 3/4 mile property is on the left.

Project Description

Please describe your proposed project:
Move dirt from the "platform" area to push to the front and also 30 cy yds total to the sides Dirt will also be moved forward on the property. The purpose is to expand the platform area to make it more usable for family activities. Dig down approximately 3 feet to accomplish this.  Some trees will be removed to accomplish this. The area to be excavated is approximately 60-100 feet long by 3 feet deep by 25-50 ft (160 cu yds). The current slope on the east and west side is about 6 to1. The ending slope will be about 4 to1. So the slope will not be steeper. There will be no shoreline impact and no wetland impact.
Will you be removing vegetation during this project? Yes

Site Drawing(s)

Land Alteration Site Sketch Checklist:
Location and size of alteration.
Attach a copy of your Site Sketch(s):

Vegetation Removal

Number of Trees to be removed: 10
Number of Shrubs to be removed: 0
Type of Clearing Used?
(Check all that apply)
Mechanical Clearing
Please explain:
Hiring an excavation company to remove the trees

Excavation Details

Nature of Material to be used?
(Check all that apply)
Other (explain below)
If other, please explain:
only moving dirt not adding any other material
Total Amount of Excavation and/or Fill proposed? (cubic yards) 166 CuYd
Total Area to be Graded and/or Filled? (L x W) 1500 ft2
Attach a photo of the area to be altered (as it exists today).:

Erosion Control Practices

Indicate the following erosion control measures that
will be used throughout and after your project?
(Check all that apply)
Seeding and/or Mulching
Other (explain below)
If other, please explain:
Slopes wont be steeper than they are now. There is no impact on shoreline and no wetland impact.
Describe how you intend to implement this plan
and your finished vegetation plan.:
The top soil from the excavated area will be applied to the slopes for erosion control purposes. Also silk fencing will be utilized around the sloped areas. This will enhance vegetative growth. Once that is established the fencing could be removed.

Other Information

Other:
miscalculation of sq yds on previous application.
 I do not have a photo of the property as it exists today. I am not able to get a photo now as I do not live near this property.

Terms

General Terms Zoning Permits
  • All appropriate permit fees must be paid in full prior to any necessary review(s) of application.

  • Defining and staking the property lines, road right-of-ways, septic sites, and wells are the responsibility of the property owner. In some cases, a registered survey may be required to verify setbacks before granting a permit.

  • To ensure that earth moving and vegetation removal is within ordinance guidelines, and to ensure activity on your property does not negatively impact the lake or other properties, you may be required to provide additional drawings of your site plan.

  • I acknowledge that by submitting this application, the application and its attachments are public information.

Land Use/Septic General Terms
  • Zoning permits and Subsurface Sewage Treatment System permits are valid for one (1) year (unless the sewage permit is to upgrade an Imminent Threat to Public Health or Safety system, which is then valid for ten (10) months).

  • If property lines are not clearly marked and visible, then they need to be staked with visible flags, ribbon, or lathes prior to onsite inspection by Aitkin County.

  • It shall be a violation of the Aitkin County Zoning Ordinance to commence construction before the permit application is approved by Aitkin County.

  • The landowner or authorized agent may make application for a zoning permit agreeing to do such work in accordance with all Aitkin County Ordinances. The landowner or authorized agent agrees that the application, site plan, and all other attachments submitted herewith are true and accurate and shall become a part of the permit. The landowner or authorized agent agrees that, in making application for a zoning permit, the landowner grants permission to Aitkin County, at reasonable times, to enter the property to determine compliance of the application with applicable Local, County or State Ordinances or Statutes. It is the applicants sole responsibility to contact other Local, County or State agencies to ensure the applicant has complied with all relevant Local, County or State Ordinances or Statutes.

  • After a complete application is submitted and reviewed, an on-site inspection may be conducted; a permit may be issued describing the proposed construction that may take place on the property. Changes to a project may require a permit application to be resubmitted.

  • Applicants are responsible for getting all applicable entrance permits from the appropriate road authority.

Invoice #55727 (07/25/2022)

Charge Cost Quantity Total
Non-Taxable
added 07/25/2022 2:42 PM

$200 Flat Fee

$200.00 x 1 $200.00
Grand Total
Total $200.00
Payment 07/25/2022$200.00
Due$0.00

Approvals

ApprovalSignature
ApplicantCharlene B. Hickerson - 08/04/2022 10:50 AM
abe343e0a3f3c42649b595126cdf42b5
13d0c3e58bd797272d75307fedd9c49d
#1 Adminstrative Approval GroupHenry Egland - 08/10/2022 4:12 PM
ba9ea5e07404800ae665488a97be96db
4ff8ba7051f7b76791d0705a5643435b
#2 Inspector GroupHenry Egland - 08/10/2022 4:12 PM
2819765fbaf5d897394edf5a7841a7a5
a513a789a5cc8ad4352a10ad00a2069b
#3 Final ActionSarah McMillan - 08/11/2022 8:15 AM
b2f2c6da1fb1965e732bedb24bea8fd0
c9b50aa318ce4b413af3c5b2058a8be8
Application has been approved. All signatures have been obtained.

Public Notes

Text:
Permit #47210

Approved for land alteration
File(s):

Internal Notes

Text:
File(s):
    Powered by