OneGov
App. Status: DeniedAitkin County Planning & Zoning / Environmental Services
307 Second St. NW Room 219
Aitkin, MN 56431
Phone: 218-927-7342
Fax: 218-927-4372
Email: aitkinpz@aitkincountymn.gov
Contact Information
If we have questions on the application who should we contact? |
|
||||||||||||||||||||||||||||||||
Are you the Property Owner? | Yes |
Project Location Search
Property: |
|
Driving directions to the property from Aitkin.: | from 169 South from Aitkin, right onto Tame Fish Rd (11), right onto w77, look for E911 sign, or Scott family sign |
Project Description
Please describe your proposed project: | Laying down Rip Rap stone along shore line of approximately 97 linear feet. estimated height of approximately 2.5 to 3 feet or whatever is allowable. No trees or vegetation to be removed. Purpose is to protect against additional shore erosion and to protect remaining trees on the shore line. |
Will you be removing vegetation during this project? | No |
Site Drawing(s)
Land Alteration Site Sketch Checklist: | Location and size of all existing structures. Location of all driveways and/or access roads. Distance of alteration to OHWL (closest point) |
Attach a copy of your Site Sketch(s): |
|
Excavation Details
Nature of Material to be used?
(Check all that apply) |
Rock Other (explain below) |
If other, please explain: | rip rap rock |
Total Amount of Excavation and/or Fill proposed? (cubic yards) | 0 CuYd |
Total Area to be Graded and/or Filled? (L x W) | 97 ft2 |
Attach a photo of the area to be altered (as it exists today).: |
|
Erosion Control Practices
Indicate the following erosion control measures that will be used throughout and after your project? (Check all that apply) |
Other (explain below) |
If other, please explain: | rip rap rock |
Describe how you intend to implement this plan and your finished vegetation plan.: |
hiring it out, professional company |
Other Information
Other: | Rip Rap rock is already on either side of the property |
Terms
Defining and staking the property lines, road right-of-ways, septic sites, and wells are the responsibility of the property owner. In some cases, a registered survey may be required to verify setbacks before granting a permit.
If you see sections marked in red on the left hand column, you must re-visit those sections and make corrections.
To ensure that earth moving and vegetation removal is within ordinance guidelines, and to ensure activity on your property does not negatively impact the lake or other properties, you may be required to provide additional drawings of your site plan.
Zoning permits and Subsurface Sewage Treatment System permits are valid for one (1) year (unless the sewage permit is to upgrade an Imminent Threat to Public Health or Safety system, which is then valid for ten (10) months).
If property lines are not clearly marked and visible, then they need to be staked with visible flags, ribbon, or lathes prior to onsite inspection by Aitkin County.
It shall be a violation of the Aitkin County Zoning Ordinance to commence construction before the permit application is approved by Aitkin County.
The landowner or authorized agent may make application for a zoning permit agreeing to do such work in accordance with all Aitkin County Ordinances. The landowner or authorized agent agrees that the application, site plan, and all other attachments submitted herewith are true and accurate and shall become a part of the permit. The landowner or authorized agent agrees that, in making application for a zoning permit, the landowner grants permission to Aitkin County, at reasonable times, to enter the property to determine compliance of the application with applicable Local, County or State Ordinances or Statutes. It is the applicants sole responsibility to contact other Local, County or State agencies to ensure the applicant has complied with all relevant Local, County or State Ordinances or Statutes.
After a complete application is submitted and reviewed, an on-site inspection may be conducted; a permit may be issued describing the proposed construction that may take place on the property. Changes to a project may require a permit application to be resubmitted.
Applicants are responsible for getting all applicable entrance permits from the appropriate road authority.
Invoice #50174 (06/12/2020)
Charge | Cost | Quantity | Total |
---|---|---|---|
added 06/12/2020 4:11 PM $200 Flat Fee |
$200.00 | x 1 | $200.00 |
Grand Total | |||
Total | $200.00 | ||
Payment 06/12/2020 | $200.00 | ||
Due | $0.00 |
Approvals
Approval | Signature | Options |
---|---|---|
Applicant | Paul E. Scott - 06/12/2020 4:12 PM bf2f8c8df9d8172a845ac242734a7042 de52e0ab23227b0c641e0be2c8f012c5 |
Text: | Denied- Erosion can be stopped with coir logs and vegetation. The addition of rip-rap cannot be granted at this time. Refund issued 6/30/20 Kb |
File(s): |
Text: | |
File(s): |
Date application was complete: | |
This review has been started by: | |
Zoning District of project location: |
Zoning Inspector: | |
Attach necessary inspection forms: | |
Is the project in the Shore Impact Zone? | |
Was an onsite conducted for this application? | |
Is this an After-The-Fact application? | |
Project located in the floodplain? | |
Base Flood Elevation: |