Land Alteration App. # App-2018-003066, UID # 195417
App. Status: Denied
Aitkin County Planning & Zoning / Environmental Services
307 Second St. NW Room 219
Aitkin, MN 56431
Phone: 218-927-7342
Fax: 218-927-4372
Email: aitkinpz@aitkincountymn.gov
 

Contact Information

If we have questions on the application who should we contact?
Name:
sherry and stuart romenesko
Phone:
(612750 - 7288
Email Address:
stuart.romenesko@kgpco.com
Mailing Address:
8800 lake riley drive
chanhassen mn 55316
Are you the Property Owner? Yes

Project Location Search

Property:
Property LocationLegal DescriptionProperty AttributesOwner InformationTax Payer Information
Parcel NumberProperty AddressTownship or City NameLegal DescriptionPlat NameSection-Township-RangeLake ClassLake NameOwner Name(s)Taxpayer Name(s)
07-0-07350243294 278TH LN
AITKIN MN 56431
FARM ISLAND TWPS:33 T:46 R:27RDFARM ISLAND LAKEROMENESKO, STUART TRUSTEEROMENESKO, STUART TRUSTEE
Driving directions to the property from Aitkin.:
Located south of Aitkin on Highway 169, approximately 12 miles south.

Off county road 77 just south of FIRM.

Off county road 77 take 278th lane.

Address 43294 278th Lane, Aitkin, MN 56431

Project Description

Please describe your proposed project:
Would like to correct work previously done by Landsburg under permit 39923 issued 9/13/13. Landsburg indicated only moved 2/3 of dirt was moved and as permitted under the original permit. In addition, we did not install nor plan to install Gazebo lakeside.

Unfortunately the 5ft access path installed to the lake does not end in a safe spot (too high) and was installed at too steep of a grade. The current path is not safe nor useable.

We would like to work with Keith Nelson from Aitkin to: (1) correct by installing a 5 ft. path switchback 2/3 of way down toward the lake to redirect path to lower and safer access point to the lake and (2) soften the steepness/incline/grade by starting the path about 10 ft. 12 ft. more in the yard.

Site Drawing(s)

Land Alteration Site Sketch Checklist:
Location and size of alteration.
Attach a copy of your Site Sketch(s):

Vegetation Removal

Number of Trees to be removed: 2
Number of Shrubs to be removed: 20
Type of Clearing Used?
(Check all that apply)
Mechanical Clearing
Hand Clearing
Please explain:
Clear small path from current access path to new proposed access path. Most vegetation are smaller trees/brush which will be pulled if possible or cut with heavy pruning shear. Chainsaw will be used to remove dead tree and larger tree if needed. We intend to keep as much natural vegetation as possible to manage the slope.

Excavation Details

Nature of Material to be used?
(Check all that apply)
Black Dirt
Gravel
Rock
Boulders
Total Amount of Excavation and/or Fill proposed? (cubic yards) 8 CuYd
Total Area to be Graded and/or Filled? (L x W) 50 ft2
Attach a photo of the area to be altered (as it exists today).:

Erosion Control Practices

Indicate the following erosion control measures that
will be used throughout and after your project?
(Check all that apply)
Silt Fence
Seeding and/or Mulching
Tree Planting
Describe how you intend to implement this plan
and your finished vegetation plan.:
Will plan to reestablish vegetation in the pathway. Use rocks and boulders to control any required retain walls and limit other brush cutting or tree/shrub removal as similar to past actions.

Terms

General Terms Zoning Permits
  • Defining and staking the property lines, road right-of-ways, septic sites, and wells are the responsibility of the property owner. In some cases, a registered survey may be required to verify setbacks before granting a permit.

  • If you see sections marked in red on the left hand column, you must re-visit those sections and make corrections.

  • To ensure that earth moving and vegetation removal is within ordinance guidelines, and to ensure activity on your property does not negatively impact the lake or other properties, you may be required to provide additional drawings of your site plan.

Land Use/Septic General Terms
  • Zoning permits and Subsurface Sewage Treatment System permits are valid for one (1) year (unless the sewage permit is to upgrade an Imminent Threat to Public Health or Safety system, which is then valid for ten (10) months).

  • If property lines are not clearly marked and visible, then they need to be staked with visible flags, ribbon, or lathes prior to onsite inspection by Aitkin County.

  • It shall be a violation of the Aitkin County Zoning Ordinance to commence construction before the permit application is approved by Aitkin County.

  • The landowner or authorized agent may make application for a zoning permit agreeing to do such work in accordance with all Aitkin County Ordinances. The landowner or authorized agent agrees that the application, site plan, and all other attachments submitted herewith are true and accurate and shall become a part of the permit. The landowner or authorized agent agrees that, in making application for a zoning permit, the landowner grants permission to Aitkin County, at reasonable times, to enter the property to determine compliance of the application with applicable Local, County or State Ordinances or Statutes. It is the applicants sole responsibility to contact other Local, County or State agencies to ensure the applicant has complied with all relevant Local, County or State Ordinances or Statutes.

  • After a complete application is submitted and reviewed, an on-site inspection may be conducted; a permit may be issued describing the proposed construction that may take place on the property. Changes to a project may require a permit application to be resubmitted.

  • Applicants are responsible for getting all applicable entrance permits from the appropriate road authority.

Invoice #45441 (05/02/2018)

Charge Cost Quantity Total
Non-Taxable
added 05/04/2018 11:37 AM

$200 Flat Fee

$200.00 x 1 $200.00
Grand Total
Total $200.00
Payment 05/04/2018$200.00
Due$0.00

Approvals

ApprovalSignature
Applicantstuart r. romenesko - 05/04/2018 11:41 AM
e18133801a3be4ee10ec55ebee78523f
0026c95edb94a527817a341a71143b85
#1 Adminstrative Approval GroupShannon Westerlund - 05/08/2018 4:11 PM
1e8235fc528dfbc17785240c2e841750
e2c273ad0dc1fd8568d1c3149d464d1c
Application has been approved. All signatures have been obtained.

Public Notes

Text:
5/30/18 application Denied. Request for a land alteration in a second lake access path does not meet the standards of the Shoreland Management Ordinance section 5.3. A refund will be issued minus a $100 inspection fee -SW
5/14 shannon did inspection, has questions
File(s):

    Internal Notes

    Text:
    shannon will do
    File(s):