Land Alteration App. # App-2017-002587, UID # 194684
App. Status: Denied
Aitkin County Planning & Zoning / Environmental Services
307 Second St. NW Room 219
Aitkin, MN 56431
Phone: 218-927-7342
Fax: 218-927-4372
Email: aitkinpz@aitkincountymn.gov
 

Contact Information

If we have questions on the application who should we contact?
Name:
Willard Temte
Phone:
(763234 - 2764
Email Address:
sarajtemte@gmail.com
Mailing Address:
3
Isanti MN 55040
Are you the Property Owner? Yes

Project Location Search

Property:
Property LocationLegal DescriptionProperty AttributesOwner InformationTax Payer Information
Parcel NumberProperty AddressTownship or City NameLegal DescriptionPlat NameSection-Township-RangeLake ClassLake NameOwner Name(s)Taxpayer Name(s)
15-0-05730034783 Nature Ave
AITKIN, MN 56431
KIMBERLY TWPS:34 T:47 R:25TEMTE, WILLARD & SARATEMTE, WILLARD & SARA
Driving directions to the property from Aitkin.:
1 mile north of County Rd 4 on County Road 53, 1st driveway on the west side of the road

Project Description

Please describe your proposed project:
Clearing trees and grinding stumps in preparation of constructing a 36x48 pole building

Site Drawing(s)

Land Alteration Site Sketch Checklist:
Location and size of alteration.
Attach a copy of your Site Sketch(s):

Vegetation Removal

Number of Trees to be removed: 25
Number of Shrubs to be removed: 0
Type of Clearing Used?
(Check all that apply)
Mechanical Clearing
Hand Clearing
Please explain:
A chainsaw will be used to remove trees that cant be removed with trimmer. large stumps may be ground and others pulled with a skid steer.

Excavation Details

Nature of Material to be used?
(Check all that apply)
Other (explain below)
If other, please explain:
May not need to being in additional material, unknown at this time.
Total Amount of Excavation and/or Fill proposed? (cubic yards) 0 CuYd
Total Area to be Graded and/or Filled? (L x W) 3500 ft2
Attach a photo of the area to be altered (as it exists today).:

Erosion Control Practices

Indicate the following erosion control measures that
will be used throughout and after your project?
(Check all that apply)
Seeding and/or Mulching
Other (explain below)
If other, please explain:
slab will be poured on a portion of the cleared area, seeding and/or mulching on the balance.
Describe how you intend to implement this plan
and your finished vegetation plan.:
Once the building is constructed, we will grade the surrounding area and seed/mulch to provide usable space.

Terms

General Terms Zoning Permits
  • Defining and staking the property lines, road right-of-ways, septic sites, and wells are the responsibility of the property owner. In some cases, a registered survey may be required to verify setbacks before granting a permit.

  • If you see sections marked in red on the left hand column, you must re-visit those sections and make corrections.

  • To ensure that earth moving and vegetation removal is within ordinance guidelines, and to ensure activity on your property does not negatively impact the lake or other properties, you may be required to provide additional drawings of your site plan.

Land Use/Septic General Terms
  • Zoning permits and Subsurface Sewage Treatment System permits are valid for one (1) year (unless the sewage permit is to upgrade an Imminent Threat to Public Health or Safety system, which is then valid for ten (10) months).

  • If property lines are not clearly marked and visible, then they need to be staked with visible flags, ribbon, or lathes prior to onsite inspection by Aitkin County.

  • It shall be a violation of the Aitkin County Zoning Ordinance to commence construction before the permit application is approved by Aitkin County.

  • The landowner or authorized agent may make application for a zoning permit agreeing to do such work in accordance with all Aitkin County Ordinances. The landowner or authorized agent agrees that the application, site plan, and all other attachments submitted herewith are true and accurate and shall become a part of the permit. The landowner or authorized agent agrees that, in making application for a zoning permit, the landowner grants permission to Aitkin County, at reasonable times, to enter the property to determine compliance of the application with applicable Local, County or State Ordinances or Statutes. It is the applicants sole responsibility to contact other Local, County or State agencies to ensure the applicant has complied with all relevant Local, County or State Ordinances or Statutes.

  • After a complete application is submitted and reviewed, an on-site inspection may be conducted; a permit may be issued describing the proposed construction that may take place on the property. Changes to a project may require a permit application to be resubmitted.

  • Applicants are responsible for getting all applicable entrance permits from the appropriate road authority.

Invoice #44704 (10/08/2017)

Charge Cost Quantity Total
Non-Taxable
added 10/08/2017 8:38 PM

$200 Flat Fee

$200.00 x 1 $200.00
Grand Total
Total $200.00
Payment 10/08/2017$200.00
Due$0.00

Approvals

ApprovalSignature
ApplicantWillard G. Temte - 10/08/2017 8:38 PM
f9afb3c5603d73e8a2ab71f177f4a99a
a9d4f1e13bdfaeb165ec0b082f666f9c

Public Notes

Text:
10.11.17 Full refund of #200 given online. KK
10/10 Talked w/ Willard. A land alteration permit is not needed; he will be applying for a land use accessory structure. App to be canceled and fully refunded. SW
File(s):

    Internal Notes

    Text:
    File(s):
      Powered by